Construction Progress Update
|
Fayrouz, Kahraman, Yakout
- Piling works completed
- Cutoff works and pile testing works completed
- Waterproofing works for footing completed
- Re-bars works for the raft footing in progress
Marmar, Amwaj, Zumourud
- Piling works completed
- Cutoff works and pile testing works completed
- Water proofing works for footing in progress
Mall and Tower
- Piling works completed
- Cutoff works and pile testing works in progress
Hotel
- Piling works in progress (70% completed)
|
|
|
|
|